Quality Control Guidelines




by James Francis Moore
Director, Construction Education Program, USGA Green Section
Quality Control. Think about those words for a minute. They describe
an effort to control or ensure quality. Now consider the construction
of a golf green. Greens construction requires a precise combination
of artistic talent, a sound scientific base, and the best in workmanship.
The reconstruction of greens is one of the most challenging projects
in the life of any course. Reconstruction represents a tremendous
opportunity for improvement of the facility. This is the chance
to correct agronomic problems such as poor drainage, inconsistency
in playing quality, weed and pest infestations, and inadequate cupping
area. It is a chance to convert to superior turfgrasses, make the
course more attractive, and make it more fun to play for all classes
of players.
Unfortunately, there also exist many opportunities to make mistakes.
Attempting to cut comers during critical aspects of reconstruction
invariably leads to problems with the new greens that soon have
everyone questioning the worth of the project. Building good greens
is not as easy as some think. There are many pitfalls that must
be avoided.
Since most of us would expect the new green to last at least 20
years and possibly much longer, quality control in the construction
of that green is critical. Who should be in charge of ensuring quality
control? Ideally, all participants in the project will strive to
do the best work possible and will constantly review their own efforts.
The architect, contractor, materials supplier, and blender all should
have quality control guidelines and procedures of their own. Certainly,
it is in their best interest to construct greens that perform properly.
Those who are paying for the new greens also have a responsibility
as consumers to be knowledgeable about what they are buying. It
is foolish to assume that the quality control efforts of the seller
(regardless of what is being sold) are sufficient to completely
protect the interests of the buyer. The buyers need someone on the
project representing only their interest. That person needs to have
a working knowledge of all aspects of the construction of greens.
They should know the area well, be in tune with the desires of those
who play the course, and have a vested interest in the success of
the project. No one fits this description better than the golf course
superintendent.
In most cases the golf course superintendent will serve as the "owners'
representative" during the reconstruction of greens. On a project
of this magnitude there is a wide variety of tasks and procedures
that must be accomplished. In most cases, there are numerous ways
to accomplish the same goal. It therefore is quite possible for
differences of opinion to arise concerning which method is best.
For the superintendent to be effective in such circumstances, the
owners must give him/her the authority to halt the project if necessary
until a consensus of opinion can be reached.
Obviously, there is a great deal to monitor during a project of
this size. Very likely it will prove impossible for the superintendent
alone to provide such close scrutiny throughout the project, particularly
on courses that remain open during construction. It therefore is
a very good idea to appoint a member of the maintenance crew as
a "clerk-of-the-works" for the duration of the project. This individual
should have no responsibilities other than providing a second set
of eyes and ears for the superintendent. Using the guidelines provided
below as a beginning, the superintendent should prepare a daily
"punch-list" for the clerk-of-the-works, detailing specific aspects
of the project to be monitored.
What follows is a checklist to help the golf course superintendent
make certain that good quality control is maintained throughout
every critical phase of a greens construction or reconstruction
project. It is important to note that not every step in the checklist
will be appropriate for every job. It is equally important to keep
in mind that this list is an example only. Every job is different,
and consequently every quality control effort must be individually
tailored to the specifics of site, individuals involved, materials,
etc. For example, on many jobs a great deal of additional testing
of materials may be necessary to meet contractual agreements. This
is particularly true in areas where the physical properties of materials
are inconsistent.
Once prepared, a quality control checklist such as this one will
help the superintendent avoid many of the mistakes commonly made
during greens construction. Space does not permit detailed discussion
of each guideline. Refer to the USGA
Green Section's Recommendations For Putting Green Construction and call your local Green Section office for additional details.



The first step to take before the reconstruction of greens that
have a history of poor performance is to ensure all the factors
responsible for that poor performance have been identified. Greens
fail for many reason. While an improved root zone mix can correct
drainage problems, it cannot provide light, air movement, or additional
surface area. Unfortunately, all too often a new green is built
without correcting many of the most limiting factors that caused
the old green to fail. The first step should be to make certain
that poor construction was the principal reason for the existing
green's poor performance. The following questions should be asked:
- Is surface drainage good?
- Do the greens drain well internally?
- Have root zone samples been submitted to a physical soil testing
lab for analysis?
- Are there layers in the profile that inhibit drainage?
- Has deep-tine aerification been tried?
- Is the existing root zone high in silt and clay?
- Is the existing root zone of consistent depth?
- Have the terminal points of the drainage tile been found and
checked for blockage?
- Has the drain tile system been flushed?
- Does sufficient light reach the turf at all times of the year?
- Is there sufficient air movement across the putting surface?
- Is the green large enough to take the traffic?
- Are there adequate entry and exit points to the green to distribute
the traffic?
- Have nutritional requirements been met?
- Has there been a check for nematodes?
- Have irrigation coverage and application needs been met?
- Could water quality problems (either physical or chemical)
be the basis for the problems?
- Have walk-behind mowers been tried instead of triplex equipment?
- Are the greens being cut too low and kept too fast?
- Is the type of grass on the greens appropriate for the demands
of your climate?
- If part of the reason for rebuilding is to eliminate Poa annua
in the greens, has Poa been controlled on the rest of the course?
- Is the membership happy with the architectural characteristics?
Remember, the desire of the players for a better design is as
much a justification for reconstruction as poor drainage.
- Has your regional Green Section agronomist been asked to examine
the greens and help identify and document the problems causing
their failure?



A. Is climate an issue? These questions
must be answered prior to selecting construction materials.
- Will the greens be maintained in a climate of extreme dryness
and high evapotranspiration rates?
- Will the greens be maintained in a climate of frequent and
prolonged wet weather, high humidity, and heat?
- Will the root zone be irrigated with water high in sodium,
salts, or both?
B. Selecting materials
- Have you personally visited local suppliers to collect samples
for submitting to a lab?
- Have you discussed with the supplier the construction of greens
so they understand the need for preciseness during the project?
- What is the source of the material?
- Is the source consistent?
- How much notice is needed to guarantee that the required quantity
and quality will be available?
- Can they stockpile the materials at their site throughout
the project, or must the stockpile be kept at the golf course
site?
- Is their stockpile area free of weeds and soil?
- Can they mix organic matter and sand, or will a custom blender
be hired?
- Will they mix the components and then wait until an outside
lab tests the mixture?
- Can they incorporate nutrients?
- Do they keep "in-house" quality control records?
- Do they use their own trucks for delivery?
- How much are shipping costs over FOB?
- To what other golf courses have they supplied material?
- Has a physical soil testing lab been located, and have their
fees and testing standards been determined?
- Does the lab test according to the procedures published by
the USGA?
- Have all of the materials (sands, organic matter, and gravel)
been submitted to the lab to verify their suitability for the
construction of greens according to the USGA Green Section recommendations?
- Has a sample been prepared according to the lab's mixing ratio
to serve as a visual "standard" throughout the project?
- If because of cost or lack of availability the proper materials
cannot be acquired, have you discussed with your Green Section
agronomist the possible repercussions of whatever compromises
must be made?
- It is likely that more than one sand and organic matter mixture
will fall within the guidelines. Have you discussed the various
mixtures available with your Green Section agronomist to help
you select the material best suited to your needs?
- Once a root zone mixture is determined, has a chemical soil
test been run to identify which nutrients should be added prior
to planting?



This is one of the most critical phases of a greens construction
project, and therefore good quality control efforts are mandatory.
What follows is a sample quality control program that will suffice
for many projects. However, note that this aspect of your quality
control program must be tailored to fit the specifics of your situation.
It may prove necessary to include much more testing throughout the
project, depending on the consistency of the materials and to meet
contractual agreements.
- Test the first load mixed to verify that the mixing procedure
is valid. The project will have to be put on hold for 24 to
48 hours while the lab verifies that the field mixing duplicates
the recommendations offered by the lab.
- Remove samples daily or anytime the mixing operation is interrupted
and compare them to the standard.
- Be prepared to mix as much of the material at one time as
possible and stockpile it.
- Each delivery truck should be inspected as the load is dumped
and the mix compared against the standard.
- Collect a one-gallon composite sample from every green, and
label and store it.
- Submit to the lab a composite sample from every third green
built.
- When moving root zone mix from stockpile into trucks, closely
monitor the loader operator to ensure that the bucket is not
collecting the underlying soil or asphalt and that cleated tires
or tracks are not "tilling" other material into the mix.



A. Location of the Green
- Will there be plenty of air movement across the green?
- Will sunlight be a problem in summer or winter?
- Will tree roots compete with the turf?
- Will there be good access to the green?
- Is there room for triplex greensmowers to turn?
- Is a perimeter irrigation system needed?
- Is the green site prone to flooding?
- Is enough surface area provided to withstand anticipated traffic?
- Are there enough hole locations?
- If not all the greens are to be rebuilt, does the design of
the new greens complement the old greens?
B. Subgrade Checks
- Are there prior construction problems such as still-functional
drain lines from the previous greens?
- Have the new drainage outlet point(s) been identified?
- Is the material to be used for the surrounding base of good
quality?
- Is the material free of large organic matter clumps and stone?
- Is the subgrade smooth and compacted?
- Are there any water-collecting hollows?
- Has the architect approved the grades?
- Has the superintendent approved the grades?
- Has the club's representative approved the grades?
- Have the grade stakes been installed and checked?
- Are the side walls of the cavity stable?
- Has the plastic barrier been installed along the side walls
of the cavity?
- Has the green perimeter location wire been installed?
- Have pictures been taken of the subgrade?
C. Tile Line Installation
- Are trenches at least 8" deep, after cleaning?
- Are bottoms of ditches smooth and clean?
- Is enough fall provided?
- Are the lateral lines within 15 feet of each other?
- Have "smile" drains been installed at each surface runoff
location?
- Has the subgrade been cleaned of soil displaced during trenching?
- Has gravel been laid and finned on the bottom of the trench?
- Are connections taped or glued?
- Are all lines completely free of buckles or bridges?
- Have lines been "shot" to ensure proper grade?
- Has the tile location wire been installed?
- Have flush points been installed, capped, and marked with
metal for future location?
- Have the perimeter and tile location wires been brought to
the main flush point?
- Has the inspection drain in front of the green been installed?
- Have pictures been taken of the finished drain tile system?
D. Gravel Layer
- Is the gravel clean and properly sized?
- Has care been taken not to crush drain lines?
- Have joints been checked to ensure they are intact after gravel
has been spread?
- Is the surface of the gravel smooth?
- Are grade stakes still intact?
- Has the finished grade of the gravel layer been checked to
ensure it "mirrors" the desired finished grade of the putting
surface?
- Have pictures been taken after gravel installation?
E. Intermediate Layer
- Has the gravel contour been preserved?
- Has the sand been kept moist during installation to help prevent
occlusion?
- Have grades been rechecked?
- Have pictures been taken?
E. Root Zone Mix
- Is the depth of the root zone mix uniform throughout the green?
- Was the mixture kept moist during installation to help prevent
occlusion?
- Has the mix been firmed?
- Have all grades been checked?
- Have amendments been added?
- Have samples of the root zone mix been collected?
- Does the finished grade mate well with surrounding soil?
G. Irrigation System
- Has single-head control been provided?
- Has coverage been checked?
- Have quick couplers been installed?
- Is a perimeter system needed?
- Have isolation valves been installed?
- Have all ditches been firmed and leveled?
H. Final Checks Prior to Planting
- Have all drains been checked?
- Have all terminal points of drains been protected?
- Have nutrients been added?
- Has the root zone mix been compacted?
- Is the irrigation system completely functional?
- Have all parties approved of final construction?
- Is certified seed or sod being used?
- Has enough root zone been stockpiled for the first year's
topdressing?
- Has all heavy equipment damage been repaired?
- Have the surrounds been sodded to prevent erosion during grow-in?
- Has fumigation been accomplished in areas prone to nematode,
nutsedge, or warmseason grass contamination problems?
A properly built USGA green can provide many years of dependable,
relatively low-cost service. Where problems have occurred with USGA
greens, often it was because shortcuts were taken or mistakes were
made without someone being aware of what was happening. Developing
and following a good quality control program is a small price to
pay for ensuring success in the construction of the most important
features of the golf course.
|
|
|
|